Fort Atkinson Bypass/State Highway 26 Corridor Expansion Project - Wisconsin

Biersdorf & Associates Project # - 3329.002
Condemning Authority - State of Wisconsin

This project is one of eight segments of construction within the State Highway 26 Corridor Expansion Project. It consists of adding two lanes and a median along the existing WIS 26 Fort Atkinson bypass for 5.5 miles from the south or north interchanges.

Bridges will be constructed at Hoard and Banker Roads to provide travel over WIS 26.

Real estate acquisition is scheduled to start in late 2008.

Construction of this segment is scheduled for fall 2010 through 2011. The estimated construction cost is $17 million (in 2006 dollars).

For further information regarding this project, call us at 866-339-7242, or visit the Wisconsin Department of Transportation website at http://www.dot.wisconsin.gov/projects/wis26corridor/exp-segment4.htm