North Tarrant Expressway Project Update

We recently spoke to a representative at the Texas Department of Transportation (TxDOT) who provided us with the following status updates for each segment of the North Tarrant Expressway (NTE) Project.

The North Tarrant Expressway Project is divided into seven segments, each with varying time-lines for property acquisition, construction and funding.    The following information is included for each segment below: project parameters, status update, and layouts/schematics detailing the proposed route and affected properties.  Also, TxDOT has released a summer 2011 NTE Master Development Plan; you can read that here:

Summer 2011 NTE Master Development Plan

Segment 1

Parameters: From IH 820 and IH 35W interchange, along IH 820 to the east and ending at the “NE Mall Interchange” (IH 820 & SH 121/183).

*Route depicted in gray on Summer 2011 NTE Master Development Plan (page 2).

Status Update: Construction has begun and they are acquiring the last few remaining properties necessary to complete this segment.

Segment 1 Layout_page 1

Segment 1 Layout_page 2

Segment 1 layout_page 3

Segment 1 Layout_page 4

Segment 1 layout_page 5

Segment 1 Layout_page 6

 

Segment 2W:

Parameters: SH121/SH 183 from IH 820 to Industrial Blvd.

*Route depicted in gray on Summer 2011 NTE Master Development Plan (page 2).

Status Update: Construction has begun and they are acquiring the remaining property necessary to complete this segment.

 

Segment 2W layout_page 1

Segment 2W layout_page 2

Segment 2W layout_page 3

Segment 2W layout_page 4

Segment 2W layout_page 5

Segment 2W layout_page 6

 

Segment 2E:

Parameters: SH 183 from Industrial Blvd to SH 161.

Status Update: There is currently no funding for property acquisition or construction, but this segment does have environmental approval. Construction is not scheduled until at least 2016 and they are unsure when property acquisition will begin as funding is not secured for this phase.

 

Segment 2E layout_page 1

Segment 2E layout_page 2

Segment 2E layout_page 3

Segment 2E layout_page 4

Segment 2E layout_page 5

Segments 3A:

Parameters: I-35W from N of I-30 to S of I-820.

Status Update: They have funding for property acquisition and they have just begun sending out offers to affected property owners. Construction has not begun but is estimated for 2011-2017.

Segment 3A layout

 

Segment 3B:

Parameters: I-35W from N of I-820 to US 81/287.

Status Update: They have funding for property acquisition and they have just begun sending out offers to affected property owners. Construction has not begun but is estimated for 2011-2017.

Segment 3B layout

Segment 3C:

Parameters: I-35W from US 81/287 to SH 170

Status Update: They currently do not have funding for property acquisition or construction. Environmental approval is underway and construction is scheduled for 2016-2020 at the earliest.  Property acquisition will commence when funding is secured for this phase.

Segment 3C layout

Segment 4:

Parameters: I-820 from SH 183 to Randol Mill Rd.

Status Update: They currently do not have funding for property acquisition or construction, but they do have environmental approval for construction.  Construction is scheduled as of now for 2021-2025.  Property acquisition will commence when funding is secured for this phase.

Segment 4 Layout


Subscribe to rss

No Comments Yet.

Leave a Reply

E-Mail Us For A Free Consultation





Your Name (required)

Your Email (required)

Subject

Phone

Your Message

captcha

Testimonials

” …It is so refreshing to know a law office that does what it says it will do…you are truly an expert in this field and I am greatful…”

- Jerald Lang,Marshfield, WI

“[I was] very satisfied. [We] got more money than the DOT offered. [It was] great working with Biersdorf & Associates.”

- Roland Thomas,Lowman, NY

“Dan listened to me; some of the attorney’s I have spoken to around my state do all the talking, but do not hear what we are saying.”

- Theresa Cornell,Milton, WV

Read More