Biersdorf & Associates Project # 3313.003
Condemning Authority: City of Madison, WI
The Pleasant View Road Extension project is in the city of Madison, WI and will consist of two intersection reconstructions, resulting in two new two-lane roudabouts.
The intersection of Pleasant View Road and Mineral Point Road will be constructed into a two-lane roundabout, and Pleasant View Road will be extended to the intersection of Valley View Road and County Trunk Highway M. This intersection will also be re-constructed into a two-lane roundabout.
An engineer from the City of Madison recently informed us that funding has been secured for the project and construction is scheduled to begin in 2010. If everything stays on schedule for the project, it is anticipated to be completed by 2011.
The project budget was recently passed by the common council, and engineers are moving forward quickly with the project. The final plans and environmental documents are in the process of being signed and completed, and engineers are finalizing right of way acquisitions for the project.
The majority of the land needed for the project was owned by the University of Wisconsin, Madison, which was dedicated to the city for the project. The remaining land needed for the project includes one property that will be acquired and an additional property that requires relocation, both of which are in the process of completion.
If you have other questions about this project, please call us at 866.339.7242 for more information. Below is a layout of the project, complimentary of the City of Madison’s website. You can visit the city’s project website by clicking here.
TRACKBACK URL FOR THIS POST:
http://www.condemnation-law.com/blog/firm-projects/wisconsin-projects/681/pleasant-view-road-extension-project-madison/trackback/

Comments on this entry are closed.